Doku Basis | Illustrative sample deliverable

Transformer impedance change: impact and closure report

This report is an illustrative product artifact created to demonstrate the proposed workflow. It contains no customer information and is not evidence of a deployed project outcome.

7affected objects
4organizations involved
12 daysto equipment release
3open approvals

Changed fact

Object
TX-01 main power transformer
Parameter
Positive-sequence impedance
Prior state
10.0% on 240 MVA base, approved design basis Rev. 06
Proposed state
11.5% on 240 MVA base, OEM submittal Rev. B
Source authority
OEM technical submittal, pending owner and utility disposition
Decision deadline
12 calendar days before manufacturing release

Impact register

ImpactReasonOwnerStatusClosure evidence
Short-circuit caseFault-current results depend on transformer impedance.Studies engineerOpenRevised case and signed review
Breaker dutyInterrupting duty must be checked against the revised case.Electrical engineerOpenRating disposition
Relay settingsProtection coordination references the prior source impedance.Protection engineerReviewApproved setting file
Utility approvalThe facilities approval package references the prior basis.Interconnection leadReviewUtility acceptance or no-impact record
OEM releaseManufacturing cannot proceed without disposition.ProcurementAt riskReleased submittal
FAT milestoneSubmittal delay consumes schedule float.Project controlsReviewUpdated integrated schedule
Commissioning basisInstalled configuration and approved model must remain aligned.Commissioning leadLinkedUpdated test prerequisite

Executive decision

Recommended disposition: Hold manufacturing release until the studies engineer completes the revised fault case and the utility or interconnection lead confirms whether the existing facilities approval remains valid. Preserve the current FAT reservation while the owner evaluates the 12-day decision window.

Audit trail

TimeEventActor
09:42OEM Rev. B ingested; impedance variance detected.Doku extraction and procurement confirmation
10:05Seven dependencies proposed with source rationale.Doku Basis
11:10Short-circuit and breaker-duty impacts confirmed.Owner's engineer
14:20Utility review assigned; equipment release placed on controlled hold.Project executive